GRP Water Tank Installation Guidelines – AQUOSYS Limited

Preparation for Installation
At AQUOSYS, we not only manufacture premium GRP water tanks, but also provide full support for proper installation to ensure structural integrity, long-term performance, and safe operation. Below are our standard recommendations for preparing the site, concrete base foundation, and clearance requirements—especially suited for East African building environments.
✅ Base Concrete Foundation Requirements
The foundation work must be completed before tank delivery and installation, and must adhere to the following criteria:
Responsibility: The client is responsible for constructing the base foundation in line with AQUOSYS specifications.
Structural Integrity: The ground must be stable and compacted, capable of supporting the full weight of the tank when filled with water.
Concrete Strength: Use concrete with a minimum compressive strength of 180 kg/cm² to ensure durability under constant load.
Surface Leveling:
The top surface must be level, with a plastered finish.
Mortar thickness should be no more than 20mm to avoid cracking or uneven weight distribution.
Standard Base Concrete Dimensions
| Component | Specification |
|---|---|
| Width | 300 – 400 mm |
| Height | Over 600 mm (including base frame) |
| Horizontal Tolerance | Less than 1/50 slope (flat horizontal) |
| Outer Dimensions | Tank dimensions + 400 mm (extra margin) |
| Spacing Between Beams | Less than 1 meter |
These standards are essential to ensure the base frame sits evenly, and the tank load is distributed uniformly, preventing structural failure or leakage over time.
Piping & Nozzle Considerations
Nozzle Locations:
Clients must specify the inlet, outlet, overflow, and drain nozzle positions and diameters at the time of placing the tank order.Custom Assembly:
AQUOSYS will pre-install the specified nozzles on the tank panels, but all external piping connections and plumbing are to be performed by the client or their appointed contractor.Connection Responsibility:
The client is responsible for ensuring proper sealing and pressure testing of all connected pipes to avoid backflow or leakage.
Installation Clearance Requirements
To ensure accessibility for maintenance, repairs, and inspections, we recommend the following minimum clearance around the tank:
| Side | Minimum Space Required |
|---|---|
| From Side Walls | At least 600 mm |
| From Ceiling/Roof | At least 1,000 mm |
Example Installation Space Requirement
For a tank of size 3m (W) x 4m (L) x 2m (H):
Minimum room size required: 3.6m (W) x 4.4m (L) x 3m (H)
This extra space allows for manhole access, panel tightening, internal inspection, and future upgrades if needed.
Why Proper Installation Matters
Prevents leaks, panel deformation, and tank failure
Ensures warranty validity
Supports hygienic and long-lasting water storage
Avoids costly retrofits or reinforcements down the line
Let AQUOSYS Support Your Site Setup
We offer optional on-site inspection services, foundation drawings, and installation supervision to make sure everything is aligned to global standards and customized for your local environment—whether in Nairobi, Kampala, Dar es Salaam, or Kigali.